| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| DALAU015 | Dala "u" 15x20x40 cms armada con una varilla de 5/8" y concreto f'c=150 kg/cm2, incluye: material, mano de obra y herramienta. | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 19BLO115 | BLOCK DALA "U" DE 15x20x40 CMS CONCRETO TIPO PESADO | PZA | 2.575000 | $11.11 | $28.61 |
| 01VAR005 | VARILLA CORRUGADA DE 5/8" | KG | 1.862400 | $8.60 | $16.02 |
| 01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.065000 | $18.00 | $1.17 |
| Suma de Material | $45.80 | ||||
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBA脩IL 1RA. | JOR | 0.050000 | $401.97 | $20.10 |
| MOA05004 | P E O N | JOR | 0.050000 | $210.17 | $10.51 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $30.61 | $1.53 |
| Suma de Mano de Obra | $32.14 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $30.61 | $0.61 |
| Suma de Herramienta | $0.61 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.014630 | $1,185.15 | $17.34 |
| BASIM003 | MEZCLA CEMENTO-ARENA 1:3 | M3 | 0.006250 | $1,510.95 | $9.44 |
| Suma de Auxiliar | $26.78 | ||||
| Costo Directo | $105.33 |