| Clave PU | Descripción del Análisis de Precio Unitario | Unidad PU |
| CCPIICO366 | Caja de caida 93 x 60 cm (libre 50 cm prof) con muro rojo, mortero cemento - arena 1:3, aplanado pulido, cadena perimetral, tapa marco y contramarco | pz |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Materiales | |||||
| CCPIIMA285 | Agua | m3 | 0.04 | 11.89 | 0.48 |
| CCPIIMA286 | Varilla de refuerzo en estructura 5/16" No. 2.5 | tramo | 0.0081 | 10100 | 81.81 |
| CCPIIMA129 | Cemento gris | t | 0.0067 | 2100 | 14.07 |
| CCPIIMA287 | Alambron | kg | 0.0067 | 13 | 0.09 |
| CCPIIMA269 | Tubo de concreto 15" s/ ref clase iii | m | 0.58 | 228.49 | 132.52 |
| CCPIIMA139 | Madera de pino 3 a 11/2x12x81/4 | pt | 1.53 | 33.59 | 51.39 |
| CCPIIMA143 | Clavo 2 1/2", 3 1/2", 3" y 4" | kg | 0.1 | 19 | 1.9 |
| CCPIIMA138 | Diesel | lt | 0.2 | 12.85 | 2.57 |
| CCPIIMA68 | Concreto hecho in - situ f'c=150 (obr urb) agreg max 38 mm | m3 | 0.31 | 1076.34 | 333.67 |
| CCPIIMA288 | Concreto hecho in - situ f'c=100 (obr urb) agreg max 38 mm | m3 | 0.213 | 975.75 | 207.83 |
| CCPIIMA283 | Aplanado y pulido en pozos de visita | m2 | 2 | 144.63 | 289.26 |
| CCPIIMA282 | Muro de tabique de 28 cm para pozo de visita | m2 | 1.53 | 267.44 | 409.18 |
| Suma de Materiales | 1524.77 | ||||
| Mano de Obra | |||||
| CCPIIMO11 | Ayudante | jor | 0.2 | 640.27 | 128.05 |
| CCPIIMO05 | Cuadrilla albañil + peón + 1/5 cabo | jor | 1 | 1855.27 | 1855.27 |
| Suma de Mano de Obra | 1983.32 | ||||
| Herramienta | |||||
| CCPIIHE01 | Herramienta menor | % | 3 | 7285.65 | 21856.95 |
| Suma de Herramienta | 21856.95 | ||||
| Costo Directo | 25365.04 |