| Clave PU | Descripci贸n del An谩lisis de Precio Unitario | Unidad PU |
| CCPIIICO24 | Excavaci贸n puot cortes y adicionales debajo de la subrasante matl c-iii roca dureza alta 6.2 - 7 mohs, prof 3 m barreno 44 mm plantilla 1.3 m | m3 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Materiales | |||||
| CCPIIIMA03 | Explosivo tovex | kg | 0.2239 | 58.93 | 13.19 |
| CCPIIIMA04 | Agente explosivo anfomex asa | kg | 0.5635 | 15.15 | 8.54 |
| CCPIIIMA05 | Cordon detonante primacord ref | m | 0.9329 | 7.13 | 6.65 |
| CCPIIIMA06 | Fulminantes del no. 6 caja 100 pz | lot | 0.0022 | 4.93 | 0.01 |
| CCPIIIMA09 | Broca 44 mm (1 3/4") en equis | pz | 0.0024 | 2173.54 | 5.22 |
| CCPIIIMA10 | Barra de extensi贸n de rosca t/ rope 5' | pz | 0.0002 | 3190.48 | 0.64 |
| CCPIIIMA11 | Coples | pz | 0.0002 | 797.37 | 0.16 |
| CCPIIIMA08 | Retiro de matl producto de voladura | m3 | 1.5 | 24.17 | 36.26 |
| Suma de Materiales | 70.67 | ||||
| Mano de Obra | |||||
| CCPIIIMO03 | Cuadrilla 2 de voladuras, 1 poblador + 2 ayudantes + 0.3 cabo | jor | 0.0082 | 2711.16 | 22.23 |
| Suma de Mano de Obra | 22.23 | ||||
| Herramienta | |||||
| CCPIIIHE01 | Herramienta menor | % | 3 | 6242.12 | 18726.36 |
| Suma de Herramienta | 18726.36 | ||||
| Equipo | |||||
| CCPIIIEQ08 | Perforadora j - 40 ingersoll rand 81 pcm broq max 7/8" x 4 1/4" de 28 kg | hr | 0.1334 | 53.69 | 7.16 |
| CCPIIIEQ09 | Compresor sullivan d 185 a 6 ca 76 hp | hr | 0.0334 | 255.14 | 8.52 |
| Suma de Equipo | 15.68 | ||||
| Costo Directo | 18834.94 |