Clave PU | Descripción del Análisis de Precio Unitario | Unidad PU |
CCPIICO465 | Estructura eléctrica t/ ‘rr’ | pz |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Materiales | |||||
CCPIIMA422 | Cruceta c4t, mca Conhesa | pz | 2 | 624.75 | 1249.5 |
CCPIIMA425 | Perno d.r.-c 16×457 mm | pz | 6 | 64.75 | 388.5 |
CCPIIMA421 | Cuerpo de cerradura cerrojo mca legrand | pz | 2 | 94.32 | 188.64 |
CCPIIMA426 | Ojo re-c | pz | 4 | 39.48 | 157.92 |
CCPIIMA427 | Moldura re | pz | 2 | 31.63 | 63.26 |
CCPIIMA428 | Grapa de remate f-8 | pz | 6 | 114.49 | 686.94 |
CCPIIMA429 | Aislador de rollo 1r | pz | 18 | 47.66 | 857.88 |
CCPIIMA419 | Aislador 13ac | pz | 1 | 315.59 | 315.59 |
CCPIIMA418 | Alfiler 1-a | pz | 1 | 49.21 | 49.21 |
CCPIIMA420 | Alambre cud-4awg thw | kg | 1 | 346.29 | 346.29 |
CCPIIMA431 | Conector de compresión yghc26c26 | pz | 3 | 115.1 | 345.3 |
CCPIIMA417 | Conector de cruz cat pi-131 | pz | 5 | 74.36 | 371.8 |
Suma de Materiales | 5020.83 | ||||
Mano de Obra | |||||
CCPIIMO39 | Cuadrilla 1/10 de electricista de primera + electricista de segunda + ayudante | jor | 1 | 1398.68 | 1398.68 |
Suma de Mano de Obra | 1398.68 | ||||
Herramienta | |||||
CCPIIHE01 | Herramienta menor | % | 3 | 7285.65 | 21856.95 |
Suma de Herramienta | 21856.95 | ||||
Equipo | |||||
CCPIIEQ141 | Grua hfm 760 k 3 p/ 6.7 ton sin Camión dodge 3500 6 ton | hr | 1 | 365.49 | 365.49 |
Suma de Equipo | 365.49 | ||||
Costo Directo | 28641.95 |