| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040238 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 15 X 15 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 15 - 4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $14.76 | $16.32 |
| 0110-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 15 - 4 | M | 1.050000 | $10.10 | $10.61 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $5.47 | $1.09 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $5.48 | $0.69 |
| 0950-05 | DIESEL | LT | 0.400000 | $4.24 | $1.70 |
| Suma de Material | $30.41 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.090900 | $564.43 | $51.31 |
| Suma de Mano de Obra | $51.31 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.023600 | $672.18 | $15.86 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.090900 | $16.06 | $1.46 |
| Suma de Auxiliar | $17.32 | ||||
| Costo Directo | $99.04 |