Clave | Descripción del Análisis de Precio Unitario | Unidad |
040632 | CASTILLO DE CONCRETO AHOGADO EN MURO DE BLOCK O TABIQUE DE PERF. VERTICAL MURO DE 12 CM (EN 2 HUECOS) CONC. F’C=150 KG/CM2-3/4″ REF. CON 2 VARILLA R.N. DE 3/8″ ESTRIBOS DE 1/4″ A/C 2 HILADAS | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 1.168000 | $4.03 | $4.71 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.156000 | $4.80 | $0.75 |
Suma de Material | $5.46 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.050000 | $564.43 | $28.22 |
Suma de Mano de Obra | $28.22 | ||||
Auxiliar | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.014000 | $672.18 | $9.41 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.025000 | $16.06 | $0.40 |
Suma de Auxiliar | $9.81 | ||||
Costo Directo | $43.49 |