| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 041221 | CELOSIA DE BLOCK CORONA DE 8 X 23 X 30 CM, ASENTADA CON MORTERO CEMENTO-ARENA 1:4 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0761-00 | CELOSIA CORONA 8 X 23 X 30 CM CON FLETE | MIL | 0.014100 | $7,575.60 | $106.82 |
| 0121-00 | REFUERZO HORIZONTAL PARA MURO DE BLOCK | M | 2.390000 | $2.68 | $6.41 |
| Suma de Material | $113.23 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.131300 | $564.43 | $74.11 |
| Suma de Mano de Obra | $74.11 | ||||
| Auxiliar | |||||
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 0.006200 | $671.58 | $4.16 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.066600 | $16.06 | $1.07 |
| Suma de Auxiliar | $5.23 | ||||
| Costo Directo | $192.57 |