| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 071606 | SUMINISTRO Y COLOCACION DE TUBO CONDUIT P.V.C. TIPO R-1 (PESADO) TRAMO 3 M 25 MM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1010-08 | TUBO CONDUIT P.V.C. TIPO R-1 ( PESADO ) TRAMO 3 M25 MM | M | 1.100000 | $14.48 | $15.93 |
| 1502-70 | SEGUETA DE ACERO | PZA | 0.048000 | $6.70 | $0.32 |
| 0082-01 | ALAMBRE GALVANIZADO NO. 14 | KG | 0.040000 | $8.46 | $0.34 |
| 3028-76 | CEMENTO PARA UNIR TUBERIA DE P.V.C. EN LATA DE 0.500 LT | LATA | 0.000800 | $120.60 | $0.10 |
| Suma de Material | $16.69 | ||||
| Mano de Obra | |||||
| 02-0840 | CUADRILLA No 84 ( 1 ELECTRICISTA + 1 AYTE. DE ELECTRICISTA ) | JOR | 0.024300 | $628.87 | $15.28 |
| Suma de Mano de Obra | $15.28 | ||||
| Costo Directo | $31.97 |