Clave | Descripción del Análisis de Precio Unitario | Unidad |
040505 | CASTILLO DE CONCRETO SECCION= 15 X 25 CM, CONCRETO F’C=200 KG/CM2-3/4″, CIMBRA 3 CARAS REFORZADO CON 4 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.834000 | $14.76 | $27.07 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.612800 | $8.32 | $13.42 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.948700 | $4.80 | $4.55 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $49.71 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.133300 | $564.43 | $75.24 |
Suma de Mano de Obra | $75.24 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.039300 | $725.61 | $28.52 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.133300 | $16.06 | $2.14 |
Suma de Auxiliar | $30.66 | ||||
Costo Directo | $155.61 |