| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070322 | SUMINISTRO Y COLOCACION DE Y DE BRONCE PARA CONEXION DE COBRE DE 51 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 3007-16 | Y DE BRONCE PARA CONEXION DE COBRE DE 51 MM | PZA | 1.010000 | $249.92 | $252.42 |
| 3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.054600 | $29.88 | $1.63 |
| 3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.012300 | $52.30 | $0.64 |
| 3037-34 | GASOLINA BLANCA | LT | 0.240000 | $7.82 | $1.88 |
| 1502-70 | SEGUETA DE ACERO | PZA | 0.117600 | $6.70 | $0.79 |
| 3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.087000 | $4.08 | $0.35 |
| Suma de Material | $257.71 | ||||
| Mano de Obra | |||||
| 02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.166600 | $628.87 | $104.77 |
| Suma de Mano de Obra | $104.77 | ||||
| Costo Directo | $362.48 |