| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| G910125-1055 | Fabricacion y estibado de trabes prefabricadas de:*1.60 x 2.60 x 32.62 m. de longitud. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 103260-1215 | Cable merlusa 6 x 36 de 3/4" | kg | 155.000000 | $143.06 | $22,174.30 |
| 103100-1030 | Cemento Tolteca CPC 30 R (cemento portland compuesto) | Ton | 0.238000 | $2,149.41 | $511.56 |
| 500310-3265 | Emulsificante fbr fester | kg | 115.355797 | $28.99 | $3,344.16 |
| 135150-3105 | Cimbrafest 19 lt | pza | 3.340500 | $871.54 | $2,911.38 |
| 103247-1035 | Agua | m3 | 0.135500 | $136.62 | $18.51 |
| 130100-1195 | Polin 3 1/4"x3 1/4"x8 1/4 | pt | 50.939201 | $9.40 | $478.83 |
| Suma de Material | $29,438.74 | ||||
| Mano de Obra | |||||
| 100100-1005 | Albañil | Jor | 12.125000 | $506.32 | $6,139.13 |
| 100100-1000 | Peón | Jor | 12.125000 | $309.53 | $3,753.05 |
| 100100-1140 | Cabo de oficiales | Jor | 1.212500 | $703.30 | $852.75 |
| Suma de Mano de Obra | $10,744.93 | ||||
| Herramienta | |||||
| 100200-1000 | Herramienta menor | (%)mo | 0.000300 | $10,744.93 | $3.22 |
| Suma de Herramienta | $3.22 | ||||
| Equipo | |||||
| C990130-2020 | Grua hidráulica con motor a diesel de 225h.p. pluma telescopica hasta 57mts. 72ton. de carga mca. grove mod. rt-880 | hr | 9.095000 | $833.51 | $7,580.77 |
| Suma de Equipo | $7,580.77 | ||||
| Concepto | |||||
| G910115-1070 | Moldes y/o cimbra metalica p/trabe cajon precolada | m2 | 222.684006 | $177.89 | $39,613.26 |
| G115100-1155 | Suministro, habilitado, colocacion acero rfrzo vars no 2 (1/4") fy=2650 kg/cm2 | kg | 132.050003 | $24.82 | $3,277.48 |
| G115100-1165 | Suministro, habilitado, colocacion acero rfrzo vars no 3-8 (3/8"-1") fy=4200 kg/cm2 | kg | 1,760.650024 | $21.93 | $38,611.06 |
| G910120-1050 | Acero de presfuerzo le>19,000 kg/cm2 | kg | 1,096.770020 | $51.70 | $56,703.01 |
| G910115-2000 | Suministro, habilitado, colocacion malla electrosoldada 6x6-4/4 | kg | 227.300003 | $19.49 | $4,430.08 |
| G910130-1045 | Suministro, habilitado, colocacion acero estruc placa a-36 | kg | 72.610001 | $32.85 | $2,385.24 |
| G910130-1050 | Suministro, habilitado, colocacion acero estruc lig redondo (rdo) a-36 | kg | 557.809998 | $33.08 | $18,452.35 |
| G905140-1020 | Concreto fc=350 kg/cm2, r.n., tma 19mm (3/4"), hecho en obra planta premezclado | m3 | 24.490000 | $1,336.54 | $32,731.86 |
| G910115-3350 | Vaciado, colado, vibrado cuerpo de estructura | m3 | 24.490000 | $461.48 | $11,301.65 |
| G910115-3360 | Curado superficies concreto | m2 | 229.832504 | $10.36 | $2,381.06 |
| Suma de Concepto | $209,887.05 | ||||
| Costo Directo | $257,654.71 |