| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070191 | SUMINISTRO Y COLOCACION DE CODO COBRE A COBRE DE 90 GRADOS DE 100 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 3003-36 | CODO COBRE A COBRE DE 90 GRADOS DE 100 MM | PZA | 1.010000 | $365.38 | $369.03 |
| 3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.073600 | $29.88 | $2.20 |
| 3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.015200 | $52.30 | $0.79 |
| 3037-34 | GASOLINA BLANCA | LT | 0.278000 | $7.82 | $2.17 |
| 1502-70 | SEGUETA DE ACERO | PZA | 0.228000 | $6.70 | $1.53 |
| 3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.106300 | $4.08 | $0.43 |
| Suma de Material | $376.15 | ||||
| Mano de Obra | |||||
| 02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.250000 | $628.87 | $157.22 |
| Suma de Mano de Obra | $157.22 | ||||
| Costo Directo | $533.37 |