Clave | Descripción del Análisis de Precio Unitario | Unidad |
040434 | CASTILLO DE CONCRETO SECCION= 10 X 20 CM, CONCRETO F’C=150 KG/CM2-3/4″, CIMBRA 3 CARAS, REFORZADA CON 4 VARILLAS R.N. DE 3/8″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.165900 | $14.76 | $17.21 |
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 2.339400 | $4.03 | $9.43 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.737900 | $4.80 | $3.54 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $5.48 | $0.69 |
0950-05 | DIESEL | LT | 0.400000 | $4.24 | $1.70 |
Suma de Material | $33.96 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.105200 | $564.43 | $59.38 |
Suma de Mano de Obra | $59.38 | ||||
Auxiliar | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.021000 | $672.18 | $14.12 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.105200 | $16.06 | $1.69 |
Suma de Auxiliar | $15.81 | ||||
Costo Directo | $109.15 |