| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 070209 | SUMINISTRO Y COLOCACION DE T DE COBRE A COBRE DE 64 MM | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 3003-88 | T DE COBRE A COBRE DE 64 MM | PZA | 1.010000 | $211.20 | $213.31 |
| 3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.072600 | $29.88 | $2.17 |
| 3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.015600 | $52.30 | $0.82 |
| 3037-34 | GASOLINA BLANCA | LT | 0.285000 | $7.82 | $2.23 |
| 1502-70 | SEGUETA DE ACERO | PZA | 0.170100 | $6.70 | $1.14 |
| 3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.105000 | $4.08 | $0.43 |
| Suma de Material | $220.10 | ||||
| Mano de Obra | |||||
| 02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.200000 | $628.87 | $125.77 |
| Suma de Mano de Obra | $125.77 | ||||
| Costo Directo | $345.87 |