Clave | Descripción del Análisis de Precio Unitario | Unidad |
040298 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 28 X 30 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS R.N. DE 1/2″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 2.210000 | $14.76 | $32.62 |
0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2″ ) | KG | 4.183200 | $4.03 | $16.86 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 1.328200 | $4.80 | $6.38 |
0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $5.47 | $1.09 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $60.23 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.200000 | $564.43 | $112.89 |
Suma de Mano de Obra | $112.89 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.088200 | $725.61 | $64.00 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.200000 | $16.06 | $3.21 |
Suma de Auxiliar | $67.21 | ||||
Costo Directo | $240.33 |