Clave | Descripción del Análisis de Precio Unitario | Unidad |
040121 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 15 CM, CONCRETO F’C=150 KG/CM2-3/4″, REFORZADA CON ARMEX DE 15 X 15-4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106000 | $14.76 | $16.32 |
0110-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 15 – 4 | M | 1.050000 | $10.10 | $10.61 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $5.48 | $0.69 |
0950-05 | DIESEL | LT | 0.400000 | $4.24 | $1.70 |
Suma de Material | $30.71 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.072700 | $564.43 | $41.03 |
Suma de Mano de Obra | $41.03 | ||||
Auxiliar | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.023600 | $672.18 | $15.86 |
Suma de Auxiliar | $15.86 | ||||
Costo Directo | $87.60 |