| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 041464 | PISO DE CONCRETO EN CUADROS ARISTAS REMATADAS CON VOLTEADOR CUADROS DE 2.00 X 1.80 M ESPESOR=5 CM CONCRETO HECHO EN OBRA F'C=150 KG/CM2-3/4" REFUERZO=MALLA 66-1010 ACABADO=SIN ACABADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,298.69 | $1.30 |
| 0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $5.46 | $5.57 |
| Suma de Material | $6.87 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $564.43 | $70.55 |
| Suma de Mano de Obra | $70.55 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.052000 | $672.18 | $34.95 |
| Suma de Auxiliar | $34.95 | ||||
| Costo Directo | $112.37 |