Clave | Descripción del Análisis de Precio Unitario | Unidad |
030415 | LOSA PLANA EN ESTRUCTURA, PERALTE = 20 CM CIMBRA COMUN REFORZADA CON 120 KG DE ACERO POR M3, CONCRETO F’C = 250 – 3/4″ | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Auxiliar | |||||
03-2080 | CONCRETO HECHO EN OBRA F’C=250 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.200000 | $782.55 | $156.51 |
Suma de Auxiliar | $156.51 | ||||
Concepto | |||||
020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. | M2 | 1.000000 | $98.59 | $98.59 |
020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8″ | TON | 0.012000 | $8,153.75 | $97.85 |
Suma de Concepto | $196.44 | ||||
Costo Directo | $352.95 |