Clave | Descripción del Análisis de Precio Unitario | Unidad |
G115100-1020 | Acero de refuerzo no 2 (1/4″) fy=2650 kg/cm2 | Ton |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
125100-1110 | Alambron 1/4″ No. 2 marca San Luis | Ton | 1.100000 | $14,721.98 | $16,194.18 |
Suma de Material | $16,194.18 | ||||
Mano de Obra | |||||
100100-1035 | Fierrero | Jor | 9.281000 | $469.91 | $4,361.23 |
100100-1015 | Ayudante general | Jor | 9.281000 | $312.55 | $2,900.78 |
100100-1000 | Peón | Jor | 1.475000 | $309.53 | $456.56 |
100100-1140 | Cabo de oficiales | Jor | 0.928100 | $703.30 | $652.73 |
Suma de Mano de Obra | $8,371.30 | ||||
Herramienta | |||||
100200-1000 | Herramienta menor | (%)mo | 0.030000 | $8,371.30 | $251.14 |
Suma de Herramienta | $251.14 | ||||
Costo Directo | $24,816.62 |