Clave | Descripción del Análisis de Precio Unitario | Unidad |
041475 | PISO DE CONCRETO EN CUADROS ARISTAS REMATADAS CON VOLTEADOR CUADROS DE 1.80 X 1.60 M ESPESOR=4 CM CONCRETO HECHO EN OBRA F’C=150 KG/CM2-3/4″ REFUERZO=MALLA 66-1010 ACABADO=PULIDO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,298.69 | $1.30 |
0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $5.46 | $5.57 |
Suma de Material | $6.87 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.142800 | $564.43 | $80.60 |
Suma de Mano de Obra | $80.60 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.041600 | $725.61 | $30.19 |
Suma de Auxiliar | $30.19 | ||||
Costo Directo | $117.66 |