Clave | Descripción del Análisis de Precio Unitario | Unidad |
G910125-1050 | Fabricacion y estibado de trabes prefabricadas de:-1.60 x 2.60 x 12.76 m. de longitud. | pza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
103260-1215 | Cable merlusa 6 x 36 de 3/4″ | kg | 155.000000 | $143.06 | $22,174.30 |
103100-1030 | Cemento Tolteca CPC 30 R (cemento portland compuesto) | Ton | 0.096500 | $2,149.41 | $207.42 |
500310-3265 | Emulsificante fbr fester | kg | 47.370602 | $28.99 | $1,373.27 |
135150-3105 | Cimbrafest 19 lt | pza | 1.451300 | $871.54 | $1,264.87 |
103247-1035 | Agua | m3 | 0.048300 | $136.62 | $6.60 |
130100-1195 | Polin 3 1/4″x3 1/4″x8 1/4 | pt | 20.653999 | $9.40 | $194.15 |
Suma de Material | $25,220.61 | ||||
Mano de Obra | |||||
100100-1005 | Albañil | Jor | 4.915000 | $506.32 | $2,488.56 |
100100-1000 | Peón | Jor | 4.915000 | $309.53 | $1,521.34 |
100100-1140 | Cabo de oficiales | Jor | 0.491500 | $703.30 | $345.67 |
Suma de Mano de Obra | $4,355.57 | ||||
Herramienta | |||||
100200-1000 | Herramienta menor | (%)mo | 0.000300 | $4,355.57 | $1.31 |
Suma de Herramienta | $1.31 | ||||
Equipo | |||||
C990130-2020 | Grua hidráulica con motor a diesel de 225h.p. pluma telescopica hasta 57mts. 72ton. de carga mca. grove mod. rt-880 | hr | 4.632900 | $833.51 | $3,861.57 |
Suma de Equipo | $3,861.57 | ||||
Concepto | |||||
G910115-1070 | Moldes y/o cimbra metalica p/trabe cajon precolada | m2 | 96.510002 | $177.89 | $17,168.16 |
G115100-1155 | Suministro, habilitado, colocacion acero rfrzo vars no 2 (1/4″) fy=2650 kg/cm2 | kg | 73.033501 | $24.82 | $1,812.69 |
G115100-1165 | Suministro, habilitado, colocacion acero rfrzo vars no 3-8 (3/8″-1″) fy=4200 kg/cm2 | kg | 973.780029 | $21.93 | $21,355.00 |
G910120-1050 | Acero de presfuerzo le>19,000 kg/cm2 | kg | 224.919998 | $51.70 | $11,628.36 |
G910115-2000 | Suministro, habilitado, colocacion malla electrosoldada 6×6-4/4 | kg | 88.910004 | $19.49 | $1,732.86 |
G910130-1045 | Suministro, habilitado, colocacion acero estruc placa a-36 | kg | 75.300003 | $32.85 | $2,473.61 |
G910130-1050 | Suministro, habilitado, colocacion acero estruc lig redondo (rdo) a-36 | kg | 557.809998 | $33.08 | $18,452.35 |
G905140-1020 | Concreto fc=350 kg/cm2, r.n., tma 19mm (3/4″), hecho en obra planta premezclado | m3 | 9.930000 | $1,336.54 | $13,271.84 |
G910115-3350 | Vaciado, colado, vibrado cuerpo de estructura | m3 | 9.930000 | $461.48 | $4,582.50 |
G910115-3360 | Curado superficies concreto | m2 | 99.131401 | $10.36 | $1,027.00 |
Suma de Concepto | $93,504.37 | ||||
Costo Directo | $126,943.43 |