| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040541 | CASTILLO DE CONCRETO SECCION= 20 X 20 CM, CONCRETO F'C=200 KG/CM2-3/4", CIMBRA 3 CARAS REFORZADO CON 4 VARILLAS A.R. DE 5/16" ESTRIBOS DE 1/4" A/C 25 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.425000 | $14.76 | $35.79 |
| 0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16") | KG | 1.612800 | $8.32 | $13.42 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.948700 | $4.80 | $4.55 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $5.48 | $0.74 |
| 0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
| Suma de Material | $58.43 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.160000 | $564.43 | $90.31 |
| Suma de Mano de Obra | $90.31 | ||||
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.042000 | $725.61 | $30.48 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.160000 | $16.06 | $2.57 |
| Suma de Auxiliar | $33.05 | ||||
| Costo Directo | $181.79 |