| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040104 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=10 X 10 CM, CONCRETO F'C=200 KG/CM2-3/4", REFORZADA CON 3 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 30 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $14.76 | $16.32 |
| 0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 1.754500 | $4.03 | $7.07 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.569200 | $4.80 | $2.73 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $5.48 | $0.69 |
| 0950-05 | DIESEL | LT | 0.400000 | $4.24 | $1.70 |
| Suma de Material | $29.90 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.080000 | $564.43 | $45.15 |
| Suma de Mano de Obra | $45.15 | ||||
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.010500 | $725.61 | $7.62 |
| Suma de Auxiliar | $7.62 | ||||
| Costo Directo | $82.67 |