| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030413 | LOSA PLANA EN ESTRUCTURA, PERALTE = 20 CM CIMBRA COMUN REFORZADA CON 120 KG DE ACERO POR M3, CONCRETO F'C = 200 - 3/4" | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.200000 | $725.61 | $145.12 |
| Suma de Auxiliar | $145.12 | ||||
| Concepto | |||||
| 020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. | M2 | 1.000000 | $98.59 | $98.59 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.012000 | $8,153.75 | $97.85 |
| Suma de Concepto | $196.44 | ||||
| Costo Directo | $341.56 |