Clave | Descripción del Análisis de Precio Unitario | Unidad |
030205 | COLUMNA EN ESTRUCTURA INCLUYE CIMBRA Y DESCIMBRA SECCION=30 X 30 CM CIMBRA COMUN REFORZADO CON 180 KG/M3 DE ACERO FY’=4200 KG/CM2 CONCRETO F’C=200 KG/CM2-3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Concepto | |||||
020211 | CIMBRA COMUN EN COLUMNAS 30 X 30 CM. | M2 | 13.333300 | $191.44 | $2,552.53 |
020323 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 5 DIAMETRO 5/8″ | TON | 0.153000 | $7,089.65 | $1,084.72 |
020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4″ | TON | 0.027000 | $9,666.38 | $260.99 |
020473 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F’C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4″ EN COLUMNAS Y MUROS | M3 | 1.000000 | $1,123.34 | $1,123.34 |
Suma de Concepto | $5,021.58 | ||||
Costo Directo | $5,021.58 |