| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040586 | CASTILLO DE CONCRETO SECCION= 28 X 20 CM, CONCRETO F'C=200 KG/CM2-3/4", CIMBRA 2 CARAS REFORZADO CON 4 VARILLAS R.N. DE 1/2" ESTRIBOS DE 1/4" A/C 25 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.101100 | $14.76 | $31.01 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 4.183200 | $4.03 | $16.86 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 1.117400 | $4.80 | $5.36 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $5.48 | $0.74 |
| 0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
| Suma de Material | $57.90 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.166600 | $564.43 | $94.03 |
| Suma de Mano de Obra | $94.03 | ||||
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.058800 | $725.61 | $42.67 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.166600 | $16.06 | $2.68 |
| Suma de Auxiliar | $45.35 | ||||
| Costo Directo | $197.28 |