| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020208 | CIMBRA COMUN EN CONTRATRABES DE CIMENTACION DE 25 X 100 CM. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.900000 | $14.76 | $42.80 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.910000 | $14.76 | $28.19 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 1.050000 | $5.75 | $6.04 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.090000 | $5.48 | $0.49 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 0.001000 | $4.03 | $0.00 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.040000 | $6.93 | $0.28 |
| 0950-05 | DIESEL | LT | 0.500000 | $4.24 | $2.12 |
| Suma de Material | $79.92 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | JOR | 0.144300 | $571.57 | $82.48 |
| Suma de Mano de Obra | $82.48 | ||||
| Costo Directo | $162.40 |