| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040128 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 20 CM, CONCRETO F'C=200 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 20-4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.196000 | $14.76 | $17.65 |
| 0111-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 20 - 4 | M | 1.050000 | $10.55 | $11.08 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.138000 | $5.48 | $0.76 |
| 0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
| Suma de Material | $33.42 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.074000 | $564.43 | $41.77 |
| Suma de Mano de Obra | $41.77 | ||||
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $725.61 | $22.86 |
| Suma de Auxiliar | $22.86 | ||||
| Costo Directo | $98.05 |