Clave | Descripción del Análisis de Precio Unitario | Unidad |
080150 | SUMINISTRO FABRICACION Y MONTAJE DE VERTEDEROS EN TANQUES DE CUPULA FIJA (INCLUYE CORTE EN CUERPO DE TANQUE.) | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0128-16 | PLACA DE ACERO ESTRUCTURAL | KG | 16.000000 | $5.28 | $84.48 |
0950-25 | GAS OXIGENO | M3 | 0.300000 | $36.12 | $10.84 |
0950-20 | GAS ACETILENO | KG | 0.030000 | $124.41 | $3.73 |
1551-35 | SOLDADURA E-6010 DE 1/8″ | KG | 0.600000 | $31.18 | $18.71 |
2600-96 | PINTURA PRIMARIA RP-2 CROMATO DE ZINC | LT | 0.600000 | $65.04 | $39.02 |
2600-86 | PINTURA ESMALTE ALQUIDALICO RA-20 | LT | 0.105000 | $27.94 | $2.93 |
2600-97 | PINTURA PRIMARIA RP-3 INORGANICA DE ZINC | LT | 0.080000 | $112.05 | $8.96 |
2600-98 | SOLUCION CURADORA PARA RP-3 | LT | 0.500000 | $38.13 | $19.07 |
0309-10 | HAMACA CON CABLE HASTA 30 M | R/D | 2.000000 | $58.00 | $116.00 |
Suma de Material | $303.74 | ||||
Mano de Obra | |||||
02-0800 | CUADRILLA No 80 ( 1 SOLDADOR CALIFICADO + 2 AYUDANTES DE SOLDADOR ) | JOR | 1.800000 | $872.92 | $1,571.26 |
Suma de Mano de Obra | $1,571.26 | ||||
Equipo | |||||
03-4210 | SOLDADOR DE ARCO ELECTRICO MILLER MODELO M1250 CD TRANSFORMADOR RECTIFICADOR | Hora | 5.810000 | $68.76 | $399.50 |
03-4220 | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | Hora | 5.810000 | $21.81 | $126.72 |
03-4321 | EQUIPO PARA APLICACION DE CHORRO DE ARENA C/ACC. | Hora | 3.000000 | $3.34 | $10.02 |
03-4322 | EQUIPO PARA APLICACION DE PINTURA POR ASPERSION C/ACC. | Hora | 3.000000 | $2.06 | $6.18 |
03-4300 | COMPRESOR PORTATIL | Hora | 3.000000 | $192.11 | $576.33 |
Suma de Equipo | $1,118.75 | ||||
Costo Directo | $2,993.75 |