Clave | Descripción del Análisis de Precio Unitario | Unidad |
030215 | COLUMNA EN ESTRUCTURA INCLUYE CIMBRA Y DESCIMBRA SECCION=50 X 50 CM CIMBRA COMUN REFORZADA CON 180 KG/M3 DE ACERO FY’=4200 KG/CM2 CONCRETO F’C=250 KG/CM2-3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Concepto | |||||
020215 | CIMBRA COMUN EN COLUMNAS 50 X 50 CM. | M2 | 8.000000 | $165.23 | $1,321.84 |
020323 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 5 DIAMETRO 5/8″ | TON | 0.153000 | $7,089.65 | $1,084.72 |
020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4″ | TON | 0.027000 | $9,666.38 | $260.99 |
020475 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F’C=250 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4″ EN CIMENTACION | M3 | 1.000000 | $1,182.56 | $1,182.56 |
Suma de Concepto | $3,850.11 | ||||
Costo Directo | $3,850.11 |