Clave | Descripción del Análisis de Precio Unitario | Unidad |
040259 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 20 X 15 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.789000 | $14.76 | $26.41 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.162800 | $8.32 | $9.67 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.843300 | $4.80 | $4.05 |
0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $5.47 | $1.09 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $44.50 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.133300 | $564.43 | $75.24 |
Suma de Mano de Obra | $75.24 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.031500 | $725.61 | $22.86 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.133300 | $16.06 | $2.14 |
Suma de Auxiliar | $25.00 | ||||
Costo Directo | $144.74 |