| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020104 | CIMIENTOS DE MAMPOSTERIA DE PIEDRA BRASA ASENTADA CON MORTERO HIDRAULICO-ARENA 1:4 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0302-70 | PIEDRA BRASA | M3 | 1.600000 | $171.83 | $274.93 |
| Suma de Material | $274.93 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.384600 | $564.43 | $217.08 |
| Suma de Mano de Obra | $217.08 | ||||
| Auxiliar | |||||
| 03-0100 | MEZCLA MORTERO HIDRAULICO-ARENA 1:4 | M3 | 0.340000 | $410.63 | $139.61 |
| Suma de Auxiliar | $139.61 | ||||
| Costo Directo | $631.62 |