Clave | Descripción del Análisis de Precio Unitario | Unidad |
041444 | PISO DE CONCRETO ARMADO DE 10 CM DE ESPESOR CONCRETO PREMEZCLADO F’C=200 KG/CM2, AGREGADO MAXIMO 3/4″ REFUERZO = VARILLA 2.5 A/C 25 CM ACABADO ESCOBILLADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0900-08 | CONCRETO PREMEZC.RN F’C=200 KG/CM2 AGREGADO MAXIMO 3/4″ (A) | M3 | 0.104000 | $1,170.00 | $121.68 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 3.379200 | $8.32 | $28.11 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.350000 | $6.93 | $2.43 |
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,298.69 | $1.30 |
Suma de Material | $153.52 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $564.43 | $70.55 |
Suma de Mano de Obra | $70.55 | ||||
Costo Directo | $224.07 |