| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010331 | TRAZO Y NIVELACION DE PLAZAS, ANDADORES, BANQUETAS Y PAVIMENTOS DE 15,001 A 20,000 M2 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.006000 | $14.76 | $0.09 |
| 0300-60 | CALHIDRA EN SACO | TON | 0.000100 | $801.61 | $0.08 |
| 1501-45 | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROL | 0.002000 | $16.45 | $0.03 |
| 2600-85 | PINTURA ESMALTE COMEX 100 | LT | 0.002000 | $36.48 | $0.07 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.000200 | $5.48 | $0.00 |
| Suma de Material | $0.27 | ||||
| Mano de Obra | |||||
| 02-0920 | CUADRILLA No 92 ( 1 AUXILIAR DE TOPOGRAFO + 4 CADENEROS ) | JOR | 0.000700 | $1,318.05 | $0.92 |
| Suma de Mano de Obra | $0.92 | ||||
| Equipo | |||||
| 03-4280 | NIVEL PARA MEDICION K-E, TIPO DUMPY, MODELO 503 | Hora | 0.005600 | $1.09 | $0.01 |
| 03-4290 | TRANSITO PARA MEDICION K-E, MODELO CH5 | Hora | 0.005600 | $1.47 | $0.01 |
| Suma de Equipo | $0.02 | ||||
| Costo Directo | $1.21 |