Clave | Descripción del Análisis de Precio Unitario | Unidad |
22400 | Suministro, colocacion y prueba de: caja de operación de valvulas de 100 x 90 cms. (Tipo 2 ) | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
AGUA-01 | AGUA (ADQUIRIDA EN PIPA) | m3 | 0.120000 | $75.79 | $9.09 |
MADERA-02 | MADERA DE PINO DE TERCERA | PT | 3.000000 | $8.08 | $24.24 |
CLAVO-01 | CLAVO DE 11/2″, 2″, 21/2″ | kg | 0.100000 | $16.17 | $1.62 |
MADERA-05 | TABLA MADERA DE PINO DE 6″x1″x8′ (TRES USOS) | PZA | 4.000000 | $16.33 | $65.32 |
ARMEX-12X12 | ARMEX 12×12-4 | ML | 9.000000 | $26.78 | $241.02 |
MATINER-01 | MATERIAL INERTE P/RELLENO. | M3 | 0.500000 | $30.32 | $15.16 |
B1EXX025 | tabique rojo recocido 7x14x28 cm. | MIL | 0.227000 | $1,601.64 | $363.57 |
APBXX020 | GRAVA de 3/4″ | M3 | 0.022000 | $237.47 | $5.22 |
Suma de Material | $725.24 | ||||
Auxiliar | |||||
MORT-005 | MORTERO CEMENTO-ARENA PROPOR. 1:4. | M3 | 0.160000 | $896.44 | $143.43 |
CONCR-200 | CONCRETO HECHO EN OBRA R.N. DE F’c=200 KG/CM2 | M3 | 0.466000 | $1,020.51 | $475.56 |
CUAD-002 | CUADRILLA No.2 1 OF. ALBAÑIL + 1 AYTE. | jor | 1.500000 | $657.83 | $986.75 |
Suma de Auxiliar | $1,605.74 | ||||
Costo Directo | $2,330.98 |