Clave | Descripción del Análisis de Precio Unitario | Unidad |
IB15ED | Cople reducción de cobre a Fo. rosca interior de 13 x 10 mm. | pieza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
DCG32 | Cople reducido de 13 x 19 (1/2″ x 3/4″) cobre int. a hierro ext. Fig. 703-R. | pieza | 1.010000 | $8.11 | $8.19 |
A5LT1 | Lija 25 mm (1″) x 1.00 m. | m | 0.041200 | $3.09 | $0.13 |
A7LEB | Soldadura 50-50 carrete. | kg | 0.003100 | $65.70 | $0.20 |
A7LEZ | Pasta fundente. | kg | 0.001500 | $48.00 | $0.07 |
A1AB1 | Gasolina Magna. | lto | 0.011000 | $4.27 | $0.05 |
A5MA1 | Sellador Filler (Lata de 0.350 kg) | kg | 0.006200 | $10.75 | $0.07 |
Suma de Material | $8.71 | ||||
Mano de Obra | |||||
F09 | Plomero | Turno | 0.027600 | $159.16 | $4.39 |
B11 | Ayudante de plomero | Turno | 0.027600 | $94.01 | $2.59 |
J02 | Cabo | Turno | 0.002760 | $164.32 | $0.45 |
Suma de Mano de Obra | $7.43 | ||||
Herramienta | |||||
03 | Herramienta | (%)mo | 0.030000 | $7.43 | $0.22 |
Suma de Herramienta | $0.22 | ||||
Costo Directo | $16.36 |