| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| VD53BB | Sotol de 100 a 150 cm. | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| XA1H2 | Sotoles de 1.00 a 1.50 m. | pieza | 1.000000 | $37.81 | $37.81 |
| Suma de Material | $37.81 | ||||
| Mano de Obra | |||||
| F14 | Jardinero | Turno | 0.027960 | $133.51 | $3.73 |
| B23 | Ayudante | Turno | 0.027960 | $94.01 | $2.63 |
| J02 | Cabo | Turno | 0.002790 | $164.32 | $0.46 |
| Suma de Mano de Obra | $6.82 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.030000 | $6.82 | $0.20 |
| Suma de Herramienta | $0.20 | ||||
| Costo Directo | $44.83 |