| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TG14BH | Pulido en parte superior de dado con llana metálica y mortero cemento-arena 1:6. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| A1A3A | Cemento gris | ton | 0.002000 | $1,182.61 | $2.37 |
| Suma de Material | $2.37 | ||||
| Mano de Obra | |||||
| B23 | Ayudante | Turno | 0.083330 | $94.01 | $7.83 |
| E01 | Oficial albañil | Turno | 0.083330 | $143.81 | $11.98 |
| J02 | Cabo | Turno | 0.008330 | $164.32 | $1.37 |
| Suma de Mano de Obra | $21.18 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.020000 | $21.18 | $0.42 |
| 26 | Andamios y ductos. | (%)mo | 0.040000 | $21.18 | $0.85 |
| 16 | Elevación | (%)mo | 0.010000 | $21.18 | $0.21 |
| Suma de Herramienta | $1.48 | ||||
| Concepto | |||||
| F2*A04 | Mortero cemento-arena 1:6. | m3 | 0.026000 | $447.91 | $11.65 |
| Suma de Concepto | $11.65 | ||||
| Costo Directo | $36.68 |