Clave | Descripción del Análisis de Precio Unitario | Unidad |
GC22BB | Muro de 10 cm de espesor aparente dos caras, blanco natural, 10 x 10 x 20 cm. | m2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
A1CBA | Tabique perforado vertical 20 x 10 x 6 cm natural Sta. Julia. | 100 | 0.480000 | $535.68 | $257.13 |
A7B32 | Varilla de refuerzo 7.9 mm ( 5/16″) diámetro. | kg | 0.470000 | $3.83 | $1.80 |
Suma de Material | $258.93 | ||||
Mano de Obra | |||||
E01 | Oficial albañil | Turno | 0.130000 | $143.81 | $18.70 |
B23 | Ayudante | Turno | 0.130000 | $94.01 | $12.22 |
J02 | Cabo | Turno | 0.013000 | $164.32 | $2.14 |
Suma de Mano de Obra | $33.06 | ||||
Herramienta | |||||
16 | Elevación | (%)mo | 0.020000 | $33.06 | $0.66 |
09 | Herramienta menor. | (%)mo | 0.020000 | $33.06 | $0.66 |
30 | Andamios. | (%)mo | 0.040000 | $33.06 | $1.32 |
Suma de Herramienta | $2.64 | ||||
Concepto | |||||
F2*A02 | Mortero cemento-arena 1:4. | m3 | 0.014000 | $578.56 | $8.10 |
F5*1B1 | Concreto F’c = 150 kg/cm2, T.M.A. de 20 mm, resistencia normal. | m3 | 0.006000 | $536.11 | $3.22 |
Suma de Concepto | $11.32 | ||||
Costo Directo | $305.95 |