Clave | Descripción del Análisis de Precio Unitario | Unidad |
IB17BG | Te de cobre a cobre de 32 mm (1 1/4″) de diámetro. | pieza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
DCK15 | Te de 32 mm. (1 1/4”) cobre a cobre a cobre int. Fig 711. | pieza | 1.010000 | $32.93 | $33.26 |
A5LT1 | Lija 25 mm (1″) x 1.00 m. | m | 0.120000 | $3.09 | $0.37 |
A7LEZ | Pasta fundente. | kg | 0.002980 | $48.00 | $0.14 |
A1AB1 | Gasolina Magna. | lto | 0.125000 | $4.27 | $0.53 |
A7LEB | Soldadura 50-50 carrete. | kg | 0.023820 | $65.70 | $1.56 |
Suma de Material | $35.86 | ||||
Mano de Obra | |||||
F09 | Plomero | Turno | 0.058820 | $159.16 | $9.36 |
B11 | Ayudante de plomero | Turno | 0.058820 | $94.01 | $5.53 |
J02 | Cabo | Turno | 0.005880 | $164.32 | $0.97 |
Suma de Mano de Obra | $15.86 | ||||
Herramienta | |||||
03 | Herramienta | (%)mo | 0.030000 | $15.86 | $0.48 |
Suma de Herramienta | $0.48 | ||||
Costo Directo | $52.20 |