| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| KM17BB | Limpieza y pintado de gabinetes de lámparas de sobreponer de 2 x 40 watts, 2 x 74 watts, 1 x 40 watts ó 1 x 74 watts. | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| P3BC3 | Esmalte sintético anticorrosivo lustral Sherwin Williams WJ21. | lto | 0.100000 | $31.99 | $3.20 |
| P3GA2 | Thinner normal Sherwin Williams. | lto | 0.200000 | $5.35 | $1.07 |
| FAZC1 | Cinta aislante de tela 5 m. | pieza | 0.050000 | $9.37 | $0.47 |
| RAC31 | Taquete de plástico de 25.4 mm (1"), # 10. | 100 | 0.020000 | $11.64 | $0.23 |
| RAC2A | Tornillo # 6, 25 mm. | 100 | 0.020000 | $13.20 | $0.26 |
| A5LT1 | Lija 25 mm (1") x 1.00 m. | m | 1.000000 | $3.09 | $3.09 |
| Suma de Material | $8.32 | ||||
| Mano de Obra | |||||
| B15 | Ayudante de electricista | Turno | 0.071000 | $94.01 | $6.67 |
| E04 | Pintor en general | Turno | 0.071000 | $133.51 | $9.48 |
| B07 | Ayudante de pintor en general | Turno | 0.071000 | $94.01 | $6.67 |
| J02 | Cabo | Turno | 0.007100 | $164.32 | $1.17 |
| H01 | Electricista en instalaciones | Turno | 0.007100 | $154.08 | $1.09 |
| Suma de Mano de Obra | $25.08 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.020000 | $25.08 | $0.50 |
| 26 | Andamios y ductos. | (%)mo | 0.040000 | $25.08 | $1.00 |
| Suma de Herramienta | $1.50 | ||||
| Costo Directo | $34.90 |