| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GC21BE | Muro de 12 cm de espesor aparente dos caras de block perforado vertical de 12 x 12 x 24 cm. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| A1BCI | Block hueco vertical 12 x 12 x 24 la Huerta. | 100 | 0.343000 | $330.00 | $113.19 |
| A7B32 | Varilla de refuerzo 7.9 mm ( 5/16") diámetro. | kg | 0.470000 | $3.83 | $1.80 |
| Suma de Material | $114.99 | ||||
| Mano de Obra | |||||
| E01 | Oficial albañil | Turno | 0.111110 | $143.81 | $15.98 |
| B23 | Ayudante | Turno | 0.111110 | $94.01 | $10.45 |
| J02 | Cabo | Turno | 0.011110 | $164.32 | $1.83 |
| Suma de Mano de Obra | $28.26 | ||||
| Herramienta | |||||
| 16 | Elevación | (%)mo | 0.020000 | $28.26 | $0.57 |
| 09 | Herramienta menor. | (%)mo | 0.020000 | $28.26 | $0.57 |
| 30 | Andamios. | (%)mo | 0.040000 | $28.26 | $1.13 |
| Suma de Herramienta | $2.27 | ||||
| Concepto | |||||
| F2*A02 | Mortero cemento-arena 1:4. | m3 | 0.011000 | $578.56 | $6.36 |
| F5*1B1 | Concreto F'c = 150 kg/cm2, T.M.A. de 20 mm, resistencia normal. | m3 | 0.007200 | $536.11 | $3.86 |
| Suma de Concepto | $10.22 | ||||
| Costo Directo | $155.74 |