Clave | Descripción del Análisis de Precio Unitario | Unidad |
IB17BK | Te de cobre a cobre de 76 mm ( 3″ ) de diámetro. | pieza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
DCK19 | Te de 76 mm (3 ”) cobre a cobre a cobre int. Fig 711. | pieza | 1.010000 | $225.98 | $228.24 |
A5LT1 | Lija 25 mm (1″) x 1.00 m. | m | 0.180000 | $3.09 | $0.56 |
A7LEZ | Pasta fundente. | kg | 0.007650 | $48.00 | $0.37 |
A1AB1 | Gasolina Magna. | lto | 0.250000 | $4.27 | $1.07 |
A7LEB | Soldadura 50-50 carrete. | kg | 0.061230 | $65.70 | $4.02 |
Suma de Material | $234.26 | ||||
Mano de Obra | |||||
F09 | Plomero | Turno | 0.076920 | $159.16 | $12.24 |
B11 | Ayudante de plomero | Turno | 0.076920 | $94.01 | $7.23 |
J02 | Cabo | Turno | 0.007690 | $164.32 | $1.26 |
Suma de Mano de Obra | $20.73 | ||||
Herramienta | |||||
03 | Herramienta | (%)mo | 0.030000 | $20.73 | $0.62 |
Suma de Herramienta | $0.62 | ||||
Costo Directo | $255.61 |