| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| IB15EE | Cople reducci贸n de cobre a Fo. rosca interior de 19 x 13 mm. | pieza |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| DCG33 | Cople reducido de 19 x 13 (3/4" x 1/2") cobre int. a hierro ext. Fig. 703-R. | pieza | 1.010000 | $9.98 | $10.08 |
| A5LT1 | Lija 25 mm (1") x 1.00 m. | m | 0.050000 | $3.09 | $0.15 |
| A7LEZ | Pasta fundente. | kg | 0.002500 | $48.00 | $0.12 |
| A1AB1 | Gasolina Magna. | lto | 0.011900 | $4.27 | $0.05 |
| A7LEB | Soldadura 50-50 carrete. | kg | 0.005000 | $65.70 | $0.33 |
| A5MA1 | Sellador Filler (Lata de 0.350 kg) | kg | 0.010000 | $10.75 | $0.11 |
| Suma de Material | $10.84 | ||||
| Mano de Obra | |||||
| F09 | Plomero | Turno | 0.035500 | $159.16 | $5.65 |
| B11 | Ayudante de plomero | Turno | 0.035500 | $94.01 | $3.34 |
| J02 | Cabo | Turno | 0.003550 | $164.32 | $0.58 |
| Suma de Mano de Obra | $9.57 | ||||
| Herramienta | |||||
| 03 | Herramienta | (%)mo | 0.030000 | $9.57 | $0.29 |
| Suma de Herramienta | $0.29 | ||||
| Costo Directo | $20.70 |