| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IB20BH | Ye de cobre a cobre de 38 mm (1 1/2") de diámetro. | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| DCT16 | Ye de 38 mm (1 1/2") cobre a cobre a cobre int. Fig. 810. | pieza | 1.010000 | $100.91 | $101.92 |
| A5LT1 | Lija 25 mm (1") x 1.00 m. | m | 0.135000 | $3.09 | $0.42 |
| A7LEZ | Pasta fundente. | kg | 0.003400 | $48.00 | $0.16 |
| A1AB1 | Gasolina Magna. | lto | 0.150000 | $4.27 | $0.64 |
| A7LEB | Soldadura 50-50 carrete. | kg | 0.027210 | $65.70 | $1.79 |
| Suma de Material | $104.93 | ||||
| Mano de Obra | |||||
| F09 | Plomero | Turno | 0.062500 | $159.16 | $9.95 |
| B11 | Ayudante de plomero | Turno | 0.062500 | $94.01 | $5.88 |
| J02 | Cabo | Turno | 0.006250 | $164.32 | $1.03 |
| Suma de Mano de Obra | $16.86 | ||||
| Herramienta | |||||
| 03 | Herramienta | (%)mo | 0.030000 | $16.86 | $0.51 |
| Suma de Herramienta | $0.51 | ||||
| Costo Directo | $122.30 |