| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AG18BC | Estudio en campo abierto o baldÃo de uso del suelo. | km/vÃa |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Mano de Obra | |||||
| T19 | Ingeniero "H" | Turno | 0.017000 | $848.65 | $14.43 |
| T17 | Ingeniero "F" | Turno | 0.033000 | $607.33 | $20.04 |
| T15 | Ingeniero "D" | Turno | 0.167000 | $461.64 | $77.09 |
| T05 | Pasante de ingeniero | Turno | 0.167000 | $261.88 | $43.73 |
| T19 | Ingeniero "H" | Turno | 0.017000 | $848.65 | $14.43 |
| T17 | Ingeniero "F" | Turno | 0.033000 | $607.33 | $20.04 |
| T15 | Ingeniero "D" | Turno | 0.167000 | $461.64 | $77.09 |
| T05 | Pasante de ingeniero | Turno | 0.167000 | $261.88 | $43.73 |
| S12 | Dibujante "C" | Turno | 0.033000 | $212.11 | $7.00 |
| T19 | Ingeniero "H" | Turno | 0.008000 | $848.65 | $6.79 |
| T17 | Ingeniero "F" | Turno | 0.017000 | $607.33 | $10.32 |
| T07 | Ingeniero "B" | Turno | 0.083000 | $328.06 | $27.23 |
| B13 | Ayudante de topógrafo | Turno | 0.333000 | $94.09 | $31.33 |
| T19 | Ingeniero "H" | Turno | 0.008000 | $848.65 | $6.79 |
| T17 | Ingeniero "F" | Turno | 0.017000 | $607.33 | $10.32 |
| T07 | Ingeniero "B" | Turno | 0.083000 | $328.06 | $27.23 |
| S12 | Dibujante "C" | Turno | 0.333000 | $212.11 | $70.63 |
| Suma de Mano de Obra | $508.22 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.030000 | $508.22 | $15.25 |
| Suma de Herramienta | $15.25 | ||||
| Equipo | |||||
| V6FG | Camioneta Pick-up con operación.Marca: Ford Modelo: F-150 | Hora | 1.333000 | $133.01 | $177.30 |
| V6FG | Camioneta Pick-up con operación.Marca: Ford Modelo: F-150 | Hora | 0.667000 | $133.01 | $88.72 |
| Suma de Equipo | $266.02 | ||||
| Costo Directo | $789.49 |