Clave | Descripción del auxiliar o básico | Unidad |
CONC0025 | CONCRETO PARA CASTILLOS Y DALAS, F’C=150 KG/CM2, T.M.A. 3/4″, HECHO EN OBRA, INCLUYE: FABRICACION, COLADO, VIBRADO Y CURADO. | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 1 | 401.97 | 401.97 |
MOA05004 | P E O N | JOR | 4 | 210.17 | 840.68 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 1242.65 | 62.13 |
Suma de Mano de Obra | 1304.78 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 1242.65 | 24.85 |
Suma de Herramienta | 24.85 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 1.03 | 1185.15 | 1220.7 |
Suma de Auxiliar | 1220.7 | ||||
Costo Directo | 2550.33 |