| Clave | Descripción del auxiliar o básico | Unidad |
| AUX-MZCHA-1:4 | Mortero cal hidratada-arena proporcion 1:4 incluye materiales y desperdicios | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MAC-005 | Cal hl datada, saco 25 kg | ton | 0.206 | 1575.08 | 324.47 |
| MAC-002 | Arena limpia | m3 | 1.1449 | 232.64 | 266.35 |
| MAC-003 | Agua (toma municipal) | m3 | 0.312 | 5.2 | 1.62 |
| MAC-005 | Cal hl datada, saco 25 kg | ton | 0.206 | 1575.08 | 324.47 |
| MAC-002 | Arena limpia | m3 | 1.1449 | 232.64 | 266.35 |
| MAC-003 | Agua (toma municipal) | m3 | 0.312 | 5.2 | 1.62 |
| Suma de Material | 1184.88 | ||||
| Costo Directo | 1184.88 |