Clave | Descripción del auxiliar o básico | Unidad |
CONCR-05 | CONCRETO HECHO EN OBRA R.N. F’c= 100 KG/CM2 | m3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
ACACT055 | CEMENTO GRIS TIPO I CEMEX O SIM. | TON | 0.278 | 1581.43 | 439.64 |
APAXX006 | ARENA | M3 | 0.514 | 121.26 | 62.33 |
GRAVA3/4 | GRAVA DE 3/4″ | M3 | 0.717 | 237.47 | 170.27 |
AGUA-01 | AGUA (ADQUIRIDA EN PIPA) | m3 | 0.222 | 75.79 | 16.83 |
Suma de Material | 689.07 | ||||
Equipo | |||||
MAQ-15 | REVOLVEDORA DE 1 SACO MCA. CIPSA MOTOR 12 HP. | hora | 0.571 | 31.65 | 18.07 |
Suma de Equipo | 18.07 | ||||
Costo Directo | 707.14 |