Clave | Descripción del auxiliar o básico | Unidad |
CAST0014 | CASTILLO AHOGADO EN HUECO DE BLOCK DE 12 CMS, DE 0.00 A 3.00 MTS DE ALTURA, CON CONCRETO F’C=150 KG/CM2 ARMADO CON UNA VARILLA DE 3/8″, INCLUYE: ACARREO, ELEVACION, ARMADO, CONCRETO, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01VAR003 | VARILLA CORRUGADA DE 3/8″ | KG | 0.6617 | 8.6 | 5.69 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.02 | 18 | 0.36 |
Suma de Material | 6.05 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.03333 | 401.97 | 13.4 |
MOA05004 | P E O N | JOR | 0.03333 | 210.17 | 7 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 20.4 | 1.02 |
Suma de Mano de Obra | 21.42 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 20.4 | 0.41 |
Suma de Herramienta | 0.41 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.01065 | 1185.15 | 12.62 |
Suma de Auxiliar | 12.62 | ||||
Costo Directo | 40.5 |